Lumut Balai Unit 2 Geothermal Plant Location : Muara Enim, South Sumatera, Indonesia

Project Details

SYSTEM

Environmental
Protection
Geosynthetic, Nets &
Anchors and Nails

TerraGreen, Armamat
Eco and Soil Nailing

OWNER

PT. Pertamina
Geothermal Energy

CONTRACTOR

PT. Wijaya Karya
(Persero) Tbk.

CONSTRUCTION YEAR

03/2024 to
06/2024

DESIGNER + CONSULTANT

  • Reinforced Earth
    (Reinforced
    Earth Indonesia)

Background

First application of Erosion Control Blanket and Protective Net for hauling road development of Lumut Balai Unit 2 Geothermal Plant.

After massive cut and fill works in hauling road development, cut and fill slope shall be protected from surface erosion issue.

In addition, some high slopes shall be stabilised with soil nailing.

Aplikasi pertama dari Selimut Pengendali Erosi dan Jaring proteksi untuk pengembangan jalan angkut Pembangkit Listrik Tenaga Panas Bumi Lumut Balai Unit 2.

Setelah pekerjaan galian dan timbunan besar- besaran dalam pengembangan jalan angkut, lereng galian dan timbunan harus dilindungi dari masalah erosi permukaan.

Selain itu, beberapa lereng yang tinggi harus distabilkan dengan soil nailing.

Challenge

Erosion Control Blanket has to be installed on slope with the height up to 50m.

Selimut Pengendali Erosi harus dipasang di lereng dengan ketinggian hingga 50m.

Solution

ReCo and FTT work together to provide combination solution soil nail and ArmaMat Eco (combination of TerraGreen and Rectangular Net) to stabilise the slopes and yet provide green facing.

In this project, we are awarded for 2,525 m2 of ArmaMat Eco, 20,890 m2 of TerraGreen and 23,415 m2 of Hydroseeding works.

ReCo dan FTT bekerja sama dalam menyediakan solusi soil nailing dan ArmaMat Eco (kombinasi TerraGreen dan Rectangular Net) untuk menstabilkan lereng dan sekaligus memberikan permukaan hijau.

Dalam proyek ini, kami berhasil memperoleh pekerjaan ArmaMat Eco seluas 2.525 m2, TerraGreen seluas 20.890 m2, dan Hydroseeding seluas 23.415 m2.